Installation and Operation Process of Integrated Prefabricated Pumping Station
Installation and Operation Process of Integrated Prefabricated Pumping Station
Make a good plan for construction area in advance
Excavation slab and outlet connecting platform
Make sure the bottom platform is flat
Pre-laying 100mm thick gravel layer at the bottom
Put in the pre-bundled steel mesh
Pre-insert eight PVC pipes and inject them with concrete
Mounting anchor bolt
Use a crane or other lifting equipment to hoist the pump
Use screws to secure the pull tabs and anchor bolts
Inject concrete into the bottom of the cylinder
Install the inlet flange to the pump inlet and connect the inlet
Pumping station backfill
Install the crushing grille (wet and dry explosion-proof motor)
Install the sewage pump at the bottom
Install the outlet flange and connect the outlet pipe
Application:
River and lake water purification and circulation
Collection and transportation of rainwater in low-lying areas of urban areas
Rainwater pollution collection and